The overall objective of the project was to implement energy saving measures in municipal buildings in the city of Chernivtsi
Nordic Environmental Finance Corporation (NEFCO)
Ukraine
02.2015-08.2015
Baseline study / Technical assessment of buildings; Training and capacity building; Assessment of alternative energy sources; Benchmarking of buildings’ energy performance; Socio economic context; Conceptual design; Definition of Priority Investment Programme and development of a long-term strategic Investment Programme; Financial projections and implications for the City budget; Procurement support