The project focuses on the installation of the Rapuni hydropower cascade comprising two small hydropower plants located at the Rapuni River in eastern Albania in the vicinity of the village of Librazhd. Both plants consist of a Tyrolean weir and a downstream desanding basin, a GRP penstock (2.9 and 3.7 km) and a power house for the turbines. The hydro-mechanical equipment was supplied by the Austrian turbine producer Kössler.
Albania
2008 – 2009
Project development (continuation of feasibility study by Posch&Partner), design for obtaining building permit and operation licences, tendering of the entire plant, execution design, structural design, consulting in all project phases
As a technical consultant, iC Ukraine provided advisory services on the reconstruction of housing for…
Experts from CES clean energy solutions, iC consulenten Ukraine and Neo Eco presented common recommendations…
The reconstruction of a dormitory in Lutsk allocated by the city for the settlement of…